Oracle’s force majeure notice puts the AI buildout’s financing chain on display

A stalled power connection at a New Mexico data centre campus has Oracle seeking to defer lease payments and its credit default swaps at a record high.

September 25, 2026Morning edition7 outlets Assembled by machine

Watercolour landscape whose skyline traces the Nasdaq Composite, 1971 to 2026, on a log scale.
Nasdaq Composite, 1971 to 2026

Oracle sent a force majeure notice on its New Mexico Stargate data centre1. The notice went to Blue Owl following a series of setbacks at the Project Jupiter campus, a 2.5GW site in New Mexico set to come online in 20282. The notice would allow Oracle to delay payments should the facility miss that 2028 target to come online1.

The cause is permitting rather than construction. Officials where the facility is being built have delayed the permits necessary to power the project, and Oracle may seek to delay lease payments as a result4. Under the terms of the contract, however, Oracle remains liable to pay data centre investors even if the site has no electricity3. Oracle stock slid after the notice was issued5.

Why it matters to investors

The episode shows where the risk in AI infrastructure actually sits. The force majeure notice on a US data centre showcases AI infrastructure risks4, because the financing rests on lease obligations that assume a site comes online on schedule1,3. When the schedule slips for reasons outside the builder’s control, the contract does not necessarily move with it3.

Lenders are exposed alongside developers. Blue Owl led a $2.4 billion AI factory financing for IREN weeks before this notice, and private credit defaults have hit a record 6.3%6. Credit markets have already marked the concern: Oracle credit default swaps hit a record high as AI debt worries mount7. Separately, Larry Ellison is set to sell up to $7.5bn worth of Oracle stock3, and his net worth is estimated at $182.1 billion5.

What to watch

The permits are the gating item. Power approvals at the site have been delayed by local officials4, so the 2028 online date and whether it holds will determine if the notice is a negotiating position or the start of a payment dispute1,2.

The contract language is the second item, because it decides who absorbs the delay. Oracle is on the hook to pay data centre investors even without electricity on site3, which means the notice and the obligation point in opposite directions. Credit spreads are the third: Oracle’s default swaps are at a record7 and private credit default rates are at a record6, so any further setbacks at Jupiter will be read through those two prices rather than through Oracle’s equity alone5.

Sources

  1. Oracle sends force majeure notice on its New Mexico Stargate data center | TechCrunch, techcrunch.com (2026-09-24)
  2. Oracle issues force majeure notice to Blue Owl following series of setbacks at Project Jupiter data center campus – report, datacenterdynamics.com (2026-09-24)
  3. Oracle on the hook to pay data centre investors even if site has no electricity, ft.com (2026-09-24)
  4. Oracle force majeure on US data center showcases AI infrastructure risks, semafor.com (2026-09-25)
  5. Oracle stock slides after company issued ‘force majeure’ notice for major data center project, forbes.com.au (2026-09-25)
  6. Bad News Keeps Piling Up For Blue Owl, As Oracle Sends Force Majeure Letter To Lender ..., finance.yahoo.com (2026-09-24)
  7. Oracle credit default swaps hit record high as AI debt worries mount - Seeking Alpha, seekingalpha.com (2026-09-24)